Watch CBS News

Report: Cost Of Upgrading Flint's Water Plant Rises To $108 Million

FLINT (WWJ/AP) - A consultant says the cost of upgrading Flint's water treatment plant is estimated at $108 million, up slightly from an earlier estimate.

The recent report by engineering and construction company CDM Smith includes $37 million for the construction of two, 21-million gallon water storage tanks and more than $34 million for pump and transfer station upgrades, The Flint Journal reported.

That figure is up slightly from a December draft report that put the cost at $105 million.

Flint will treat Lake Huron water from a new pipeline. The plant improperly treated water from the Flint River in 2014-2015, leading to the city's crisis with lead-tainted water.

The report estimates work on the plant can be completed in 2019-2020. The state Department of Environmental Quality must agree to the final version of the consultant's report.

TM and © Copyright 2017 CBS Radio Inc. and its relevant subsidiaries. CBS RADIO and EYE Logo TM and Copyright 2017 CBS Broadcasting Inc. Used under license. All Rights Reserved. This material may not be published, broadcast, rewritten, or redistributed. The Associated Press contributed to this report.

View CBS News In
CBS News App Open
Chrome Safari Continue
Be the first to know
Get browser notifications for breaking news, live events, and exclusive reporting.