Phase 2 Of I-75 Construction Begins Friday: What To Know

MICHIGAN (CBS DETROIT) - The process of switching northbound I-75 traffic to its pre-construction configuration began at 7 a.m. Friday, Dec. 27.

By the end of the day on Tuesday, Dec. 31, it is expected that northbound I-75 traffic will be using the new northbound pavement with three lanes open except for a 1-mile stretch from Big Beaver to Wattles roads, where only two lanes will be open due to the ongoing construction of a noise wall through the winter months. Northbound exit ramps are expected to open as work progresses.

Additionally, southbound I-75 will be reduced to one lane starting at 7 a.m. on Friday to continue the process to have all southbound lanes and ramps open by the end of the calendar year.

Crews need to remove roughly 9 miles of temporary concrete barrier wall off the southbound lanes and restripe the freeway before fully opening travel lanes and ramps. To safely complete this work, southbound I-75 will have one lane open until 7 p.m. Tuesday, Dec. 31.

At that time, all exit and entrance ramps on both sides of the freeway will open to traffic.

Currently, both directions of I-75 are sharing the southbound side of the freeway, separated by a temporary concrete barrier between 13 Mile Road and Coolidge Highway. Two lanes are open in each direction.

This $224 million project involves reconstructing more than 8 miles of pavement in each direction, improving 18 structures, upgrading drainage, constructing community-developed aesthetics and federally approved noise walls, and continuing construction of an additional travel lane between Coolidge Highway and 13 Mile Road.

© 2019 CBS Broadcasting Inc. All Rights Reserved. This material may not be published, broadcast, rewritten, or redistributed.

View CBS News In
CBS News App Open
Chrome Safari Continue
Be the first to know
Get browser notifications for breaking news, live events, and exclusive reporting.